Construction on the Highway 17 Keating Cross overpass project will resume Wednesday, April 1, 2026, after a short winter break.
Drivers are reminded this is an active construction zone.
The on-ramp and off-ramp at Exit 18 (Keating flyover) are expected to remain open during daytime hours while remaining work is completed. Periodic nighttime closures will be required:
- Nightly lane closures will happen in each direction along Highway 17 between Tanner Road and Island View Road, resulting in:
- single-lane northbound traffic from 7 p.m. until 6 a.m.
- single-lane southbound traffic from 9 p.m. until 6 a.m.
The project is expected to be complete in spring 2026.
People are asked to take extra care when travelling through the area, watch for workers and equipment, and obey signage.
Any closures or traffic pattern changes will be shared with the public when possible, at www.DriveBC.ca and on the project webpage at www.gov.bc.ca/keatingoverpass