Transportation and Infrastructure

New bridges to prevent highway washouts

Print

Transportation and Infrastructure

New bridges to prevent highway washouts

Updated on July 24, 2019

Media Contacts
Ministry of Transportation and Infrastructure
Media Relations
Government Communications and Public Engagement
250 356-8241
(flickr.com)
Media Contacts
Ministry of Transportation and Infrastructure
Media Relations
Government Communications and Public Engagement
250 356-8241

Backgrounders

2016 Peace Flood Recovery Program

Completed major transportation infrastructure projects include:

Commotion Creek Bridge (near Chetwynd)
Project: replacement of existing culvert with a two-lane, 38-metre long bridge
Budget: $7.3 million
Completed: 2019

Stone Creek Bridge (near Chetwynd)
Project: replacement of the existing culvert with a two-lane, 19-metre long bridge
Budget: $4.6 million
Completed: 2019

Tippy Corner Creek Bridge (near Chetwynd)
Project: replacement of the existing culvert with a two-lane, 17.5-metre long bridge
Budget: $3.8 million
Completed: 2019

Willow Flats Bridge (near Chetwynd)
Project: replacement of the existing culvert with a two-lane, 13.5-metre long bridge
Budget: $4 million
Completed: 2019

Zonnebeke Creek (near Chetwynd)
Location: replacement of the current three-metre culvert with a 6.4-metre one
Total project cost: $12 million
Completed: 2018

Walper Bridge (near Pouce Coupe)
Project: construction of a new single-lane, 25-metre bridge at Tupper Creek, to replace the original Walper bridge, which was washed out in the June 2016 flood
Total project cost: $4.2 million
Completed: 2018

Projects in various stages of construction (as of July 15, 2019):

Bowlder Creek Bridge (west of Chetwynd)
Project: replacement of the existing culvert with a two-lane, 30.5-metre long bridge
Budget: $7.1 million
Contractor: Formula Contractors Ltd.
Anticipated completion date: fall 2019

Rolla Road (east of Dawson Creek)
Project: replacement of the existing bridge with a two-lane, 50-metre long bridge that crosses Dawson Creek
Budget: $20 million
Contractor: Brocor Construction Ltd.
Anticipated completion date: fall 2019

Parnell Bridge (north of Dawson Creek)
Project: replacement of two existing culverts with a new two-lane, 40-metre long bridge
Budget: $4 million
Contractor: Surespan Construction Ltd.
Anticipated completion date: winter 2019

Connect with the Ministry

Photos

View the Ministry's latest photos on Flickr.

Videos

Watch the Ministry's latest videos on YouTube.

Sound Bites

Listen to the Ministry's latest audio clips on SoundCloud.

View all Social Media