Broadway Subway Project key construction timelines
  • Spring 2021-early 2022: construction of traffic decking in station blocks on Broadway.
  • 2021-23: elevated guideway construction to connect with VCC-Clark Station.
  • Mid-2022: assembly and launch of the tunnel-boring machines.
  • Summer 2022-mid 2023: tunnel-boring machines arrive at stations on Broadway.
  • Summer 2023: tunnel-boring machines disassembled/removed near Arbutus Station.
  • 2023-24: construction of station structures and interiors.
  • 2024: removal of traffic decking and restoration of roads and streetscape.
  • 2024: installation of tracks.
  • 2025: testing of train operating system and grand opening.