Royal Columbian Hospital redevelopment timelines

Phase 1, through to 2019:

  • Adds mental health care capacity and also prepares for future expansion.
  • The new 20,600 square metre (221,736 square foot) mental health and wellness use centre will have three floors of inpatient units including 45 beds for acute mental health care, a 10-bed psychiatric high acuity unit, and Fraser Health’s first older adult psychiatric unit with 20 beds.
  • One floor of the facility will house 12 outpatient clinics, many of them new or expanded, plus clinical education space.
  • An underground parkade, new energy centre for power and utilities, and a new IT communications server hub will also be part of the facility and serve the entire hospital.

Phase 2, 2020-2024:

  • Adds acute care capacity.
  • A new acute care tower will add more beds for critical care, maternity, medicine and surgical patients, plus a new emergency department, more operating rooms, more interventional suites for cardiology and radiology, more MRIs, a new main entrance, an underground parkade, and a rooftop heliport.

Phase 3, 2023-2026:

  • Expands existing spaces.
  • The third phase will expand the neonatal intensive care unit, pediatric unit, laboratory, pharmacy, diagnostic services, food services, ambulatory care services and other service support areas.
  • Four-bed patient rooms in Columbia Tower will be converted to private or semi-private rooms.
  • The acute care tower, health-care centre and Columbia Tower will be connected on three levels, creating a super-floor for interventional and surgical services, and another super-floor for families.